Saturday, 28th of July 2018 - Power cable is finally placed in soil.
Saturday, 21st of July - A few of terrain modifications.
Wednesday, 11th of July 2018 - There were 3 days without electricity and a public holiday last week. A small progress is visible today.
Thursday, 28th of June 2018 - it starts to get a shape of house.
Tuesday, 26th of June 2018 - The building is growing again.
Friday, 22nd of June 2018 - the bricks were delivered. The row number 6 was built. The drainage was placed together with nopova film.
Thursday, 31st of May 2018 - last rows of bricks before waiting for their delivery.
Wednesday, 30th of May 2018 - another two rows are added.
Friday, 25th of May 2018 - the bricks were delivered on the building place.
Friday, 18th of May 2018.
The base of our home is done. Now the construction should move up a little quicker. The sheets of waterproofing has been placed on the base. When the weather allows it, the walls will rise up.